Construction
& Building Works

The building
is constructed predominantly of red brick and sand stone, with pitched slate
roof.
The
eaves of the main building are approximately 30 to 40 feet above the ground level
(the site slopes away from the road), with a brick dentil course forming the
basis of the support for the rainwater drainage goods, which are cast iron.
In
the recent past four major projects of building work have been undertaken,
other minor projects are ongoing:
Ø
The
sandstone parapets at the front of the church had slipped causing some masonry
damage at the corners. The remedial work
was carried out and the sandstone blocks reset and tied into the
brickwork. Specialist contractors
completed the works, which were funded solely by the church.
Ø
Dry
rot was found behind panelling during an inspection of timber. The infected timber and a large section of
plaster were replaced and followed by a major program of redecoration. Specialist contractors completed the works, which
were funded solely by the church using a bequest from an ex-member.
Ø
A
toilet suitable for use by the disabled was created from the Gents
facilities. This involved moving a door
opening and a reorganisation of the plumbing in addition to installing the
necessary specialist fittings. Members
and friends completed the works, which were funded both by the church and grant
assistance. This funding assistance is
recognised with a thank-you certificate displayed next to the entrance.
Ø
The
entrance vestibule was enlarged to form a separate meeting room at the front of
the church by constructing a stud wall at the level of the front of the balcony. This room was fitted with independent central
heating and a small kitchen area to enable it to be self contained for small
meetings. The sisterhood and Thursday
prayer meeting use the room regularly.
The whole of the works were undertaken by members and friends and funded
by the church.
Ø In spring of 2007 Erskine & Hurt Consultants Ltd, Civil and Structural Engineers, were commissioned to carry out a survey of the roof. Their recommendations were for either major repairs or a replacement of the roof and rainwater goods. Grants were sought to enable a recovering of the roof with eternit slate tiles on felt underlay along with repairs to the brickwork and new rainwater goods. The loft space was also given a layer of insulating material to conserve heat. This project was undertaken in February/March 2009.
Ø Ground floor windows in the rear of
the building were replaced by new uPVC units made to
be sympathetic to the existing building in 2010. A specialist contractor undertook the work,
funded by the church.